Follow the decisions, announcements, and changes surrounding the planned lead azide detonation at the Iowa Army Ammunition Plant.
Most recent events first. Each entry links to its supporting sources.
Where things stand
Tentative detonation · about Nov 25, 2026, 09:00 CST.
- Latest developments
- Detonation date
- November 25, 2026, 09:00 Central, tentative. Source: Army plans detonation for November 25 at about 9 a.m..
- Detonation confirmed
- No. This timeline has no confirmed report that the detonation has happened.
- Checked through
- November 24, 2026, 16:45 UTC · review record
Status note from the latest record
The Army's November 24 advisory says it plans to carry out the controlled detonation on Wednesday, November 25, at approximately 9:00 a.m. CST, with a more precise time to follow after it evaluates the weather. FEMA is supporting a recommended relocation for residents of Middletown and the immediately surrounding area (a 5-mile cone southwest of the plant); people outside that zone are encouraged to shelter in place. The detonation has not been reported as having occurred.
November 2026
-
· Announcement
Army plans detonation for November 25 at about 9 a.m.
The Army's November 24 public safety advisory says it plans to carry out the controlled detonation on Wednesday, November 25, 2026, at approximately 9:00 a.m. CST, and will give a more precise time after evaluating the weather. FEMA is supporting a recommended relocation, starting November 24, for residents of Middletown and the immediately surrounding area: a 5-mile cone southwest of the plant, extended one mile beyond the modeled dispersion path. People outside that zone are encouraged to shelter in place. The Army also published updated projection maps and says it will update them six hours before the detonation and hourly after that. This record does not report that the detonation has occurred.
Source: Army public advisory, November 24, 2026 (army.mil article 297039) · archived copy
Additional sources & record details
- Effective
- November 24, 2026, 09:06 Central
- Published
- November 24, 2026, 09:06 Central
- Event status at the time
- Not yet happened · announced date November 25, 2026, 09:00 Central (Army: 'at approximately 9:00 a.m. CST'; a more precise time is to follow after weather evaluation.)
Sources
- Army public advisory, November 24, 2026 (army.mil article 297039)
- Army public advisory, November 24, 2026 (army.mil article 297039)
- Army public advisory, November 24, 2026 (army.mil article 297039)
- Army public advisory, November 24, 2026 (army.mil article 297039)
- Army Sustainment Command: Iowa Army Ammunition Plant updates index (supporting source)
- Iowa Lead Azide Detonation: Missouri response page (supporting source)
- Iowa Army Ammunition Plant: Illinois updates page (supporting source)
- Army public advisory: mitigated surface deposition and air dispersion maps, issued November 24, 2026 (PDF) (context)
Army projection maps for the November 25 plan: mitigated surface deposition and air dispersion (issued November 24, 2026)
Computer-modeled predictions for a mitigated detonation (in a bunker with added countermeasures), not measurements. Surface deposition: about 27 square miles above 100 µg/ft² (labeled EPA's maximum for lead on windows) and 148 square miles above 5 µg/ft² (EPA's maximum for floors). Air dispersion is drawn at 1, 4 and 8 hours after detonation, outlined at 0.18 µg/m³ (labeled the detection limit of the lead air sampling method). Both maps draw the modeled plume extending southwest of the plant. The maps advise avoiding the highlighted area or staying indoors with windows and doors closed, and waiting for the Army's all-clear.
- Published
- November 24, 2026 by U.S. Army
- Made for
- November 25, 2026 plan (Army advisory of November 24)
- Status
- Current
- Map coverage
- Document only (images in a PDF); not drawn on the map
- Verification
- Verified
- Record
prj-army-2026-11-24-mitigated-maps· added to this timeline 2026-11-24 16:42 UTC
- Army public advisory: mitigated surface deposition and air dispersion maps, issued November 24, 2026 (PDF)
- Army public advisory: mitigated surface deposition and air dispersion maps, issued November 24, 2026 (PDF)
- Army public advisory: mitigated surface deposition and air dispersion maps, issued November 24, 2026 (PDF)
- Army public advisory, November 24, 2026 (army.mil article 297039) (supporting source)
- Army Sustainment Command: Iowa Army Ammunition Plant updates index (supporting source)
- DVIDS listing: Iowa Army Ammunition Plant publication, November 24, 2026 (issue 78382) (supporting source)
- Added to this timeline
- 2026-11-24 16:42 UTC
- Record
evt-2026-11-24-army-advisory
-
· Schedule status
Army's last published target date: November 25
The Army's last published target date for the detonation is November 25, 2026, from its November 22 notice. No later authoritative statement confirming or changing it has been captured since the reported pause of November 23.
The current status is not confirmed. No time has been announced in the material held here.
Date replaced by a later announcement: Army plans detonation for November 25 at about 9 a.m.
Source: Army public advisory (November 22)
Additional sources & record details
As recorded
The Army's last published target date for the detonation is November 25, 2026, from its November 22 notice (date only; no time in the material held here). After the reported presidential pause of November 23, no later authoritative statement confirming or changing that date has been captured, so the current status is not confirmed. The project owner reported on November 24 that the date had not changed; that report is recorded in rev-event-status-2026-11-24-owner-date and is not itself a captured source. This record does not report that the detonation has occurred.
- Event status at the time
- Unclear · announced date November 25, 2026 (The Army's last published target date (November 22 notice); not confirmed after the reported pause.)
Sources
- Army public advisory (November 22)
- Iowa HHS: Lead Exposure & Surveillance (supporting source)
- Axios report on the November 23 delay (title not captured; URL slug "iowa-lead-detonation-delayed-trump") (context)
- Opinion (per curiam), Iowa Environmental Council v. EPA, No. 26-3374, filed November 23, 2026 (Entry ID 5708974) (context)
- Added to this timeline
- 2026-11-24 15:06 UTC
- First added
- 2026-11-24 14:43 UTC
- Record
evt-2026-11-24-nov-25-date-stands.r1
View correction history (1 earlier version)
Version added 2026-11-24 14:43 UTC
- Headline then
- Army's November 25 date still stands
- Date then
- November 24, 2026
- Description then
- As of November 24, 2026, the Army's most recent public schedule is its November 22 notice moving the detonation to November 25, 2026, and no later Army statement changing that date has been found. The project owner confirmed on November 24 that the date has not changed. No time has been announced in the material held here. News reports on November 23 said the President directed the Army to pause pending agreement from the Eighth Circuit and Iowa Governor-elect Rob Sand; later that day the Eighth Circuit lifted its temporary hold on the EPA permit. This record restates the current schedule; it does not report that the detonation has occurred.
- What changed and why
- Reviewer (2026-11-24): the captured evidence supports the Army's last published target date at day precision, not that the date still stands after the reported pause. The earlier record's 'we confirmed' rested on the project owner's report, which is not a captured source. Retitled as the last published target date and the status kept unconfirmed until a later authoritative confirmation is captured.
- Updated by
evt-2026-11-24-nov-25-date-stands.r1, added 2026-11-24 15:06 UTC- Record
evt-2026-11-24-nov-25-date-stands
- Army public advisory (November 22)
- Iowa HHS: Lead Exposure & Surveillance (supporting source)
- Axios report on the November 23 delay (title not captured; URL slug "iowa-lead-detonation-delayed-trump") (context)
- Opinion (per curiam), Iowa Environmental Council v. EPA, No. 26-3374, filed November 23, 2026 (Entry ID 5708974) (context)
-
· News reports
President reportedly directs Army to pause detonation
News reports said the President directed the Army to pause the detonation until the Eighth Circuit and Iowa Governor-elect Rob Sand agree.
These are news reports, not an official announcement or a court decision. No replacement date appears in the material reviewed.
Additional sources & record details
As recorded
News reports on November 23 said the President directed the Army to pause the detonation pending agreement from the Eighth Circuit and from Governor-elect Rob Sand. No confirmed replacement date appears in the material reviewed. These are news reports, not a court ruling on the merits.
- Event status at the time
- Paused
Sources
- Axios report on the November 23 delay (title not captured; URL slug "iowa-lead-detonation-delayed-trump")
- Washington Post: Trump orders military to halt Iowa detonation plan (supporting source)
- AP report: presidential direction to pause the detonation pending court approval (updated later)
- Added to this timeline
- 2026-11-24 00:17 UTC
- First added
- 2026-11-23 23:22 UTC
- Record
evt-2026-11-23-reported-pause.r1
View correction history (1 earlier version)
Version added 2026-11-23 23:22 UTC
- Headline then
- Pause reported by AP
- Date then
- November 23, 2026
- Description then
- AP reported that the President directed a pause pending agreement from the Eighth Circuit and from Governor-elect Rob Sand. No confirmed replacement date appears in the material reviewed. The Washington Post independently reported the halt. These are news reports, not a court ruling on the merits.
- What changed and why
- The AP URL first cited for the pause was later updated to lead with a subsequent Eighth Circuit ruling (project owner recheck, 2026-11-24). The pause is now cited to contemporaneous reporting; the AP link is kept and labeled as updated.
- Updated by
evt-2026-11-23-reported-pause.r1, added 2026-11-24 00:17 UTC- Record
evt-2026-11-23-reported-pause
-
· Court decision
Federal appeals court lifts temporary hold on EPA permit
The Eighth Circuit turned down the request for an emergency stay and lifted its temporary hold on the EPA permit, finding that those challenging the permit had not shown they were likely to win.
The court did not decide the underlying legal challenge, did not set a detonation date, and did not rule on the Army's stated plan to use the emergency exception. The ruling does not mean the detonation has happened.
Source: Opinion (per curiam), Iowa Environmental Council v. EPA, No. 26-3374, filed November 23, 2026 (Entry ID 5708974) · archived copy
Legal details & supporting records
As recorded
In No. 26-3374 the Eighth Circuit (per curiam; Judges Shepherd, Grasz and Smith) denied the petitioners' emergency motion to stay the EPA emergency permit pending review and lifted its administrative stay, concluding the petitioners had not shown they were likely to prevail. The petition for review itself was not decided. The court said it could not and did not opine on the Army's separately stated intent to act under RCRA's emergency exclusion, because the Army is not a party. The ruling does not set a date for the detonation and does not report that it occurred.
- Event status at the time
- Unclear
Sources
- Opinion (per curiam), Iowa Environmental Council v. EPA, No. 26-3374, filed November 23, 2026 (Entry ID 5708974)
- Opinion (per curiam), Iowa Environmental Council v. EPA, No. 26-3374, filed November 23, 2026 (Entry ID 5708974)
- Opinion (per curiam), Iowa Environmental Council v. EPA, No. 26-3374, filed November 23, 2026 (Entry ID 5708974)
- Clerk's transmittal letters with the opinion, No. 26-3374, November 23, 2026 (Entry ID 5708974) (supporting source)
- Axios report on the November 23 delay (title not captured; URL slug "iowa-lead-detonation-delayed-trump") (context)
- Added to this timeline
- 2026-11-24 00:35 UTC
- Record
evt-2026-11-23-eighth-circuit-denies-stay
-
· Schedule change
Army reschedules detonation for November 25
The Army moved the planned detonation to November 25. No time was announced; Iowa HHS said the date and time remained pending an Army announcement.
Followed by news reports of a pause: President reportedly directs Army to pause detonation
Source: Army public advisory (November 22)
Additional sources & record details
As recorded
The Army publicly moved the plan to November 25, 2026. No time was announced; Iowa HHS stated the date and time remained pending an Army announcement.
- Event status at the time
- Not yet happened · announced date November 25, 2026
Sources
- Army public advisory (November 22)
- What Midwest residents need to know about the lead azide detonations planned for this week (supporting source)
- Iowa HHS: Lead Exposure & Surveillance (supporting source)
- Added to this timeline
- 2026-11-23 23:22 UTC
- Record
evt-2026-11-22-army-moves-plan
-
· Court filing
Army states intent to proceed under emergency exception
In a notice the Justice Department filed in the court case, the government said the Army intended to rely on an emergency exception in federal hazardous-waste law, which would let it carry out the detonation without the challenged permit, and to act by November 24.
This was a statement of intent, not court approval. The court later said it could not and did not rule on it.
Source: Respondents' Notice of the Army's Intent to Respond to Immediate Threat Under RCRA's Emergency Exclusion, with Declaration of Col. Aaron C. Teller, No. 26-3374, filed November 21, 2026 (Entry ID 5708596) · archived copy
Legal details & supporting records
As recorded
A Justice Department notice filed in No. 26-3374 on November 21 said the Army intended to invoke RCRA's emergency munitions and explosives exclusion, under which it could perform the controlled detonation without the challenged emergency permit, and to act "by" (elsewhere "on") November 24, 2026, consistent with the permit's terms and mitigation measures. This was a stated intent, not court approval; the court later said it could not and did not opine on it.
Sources
- Respondents' Notice of the Army's Intent to Respond to Immediate Threat Under RCRA's Emergency Exclusion, with Declaration of Col. Aaron C. Teller, No. 26-3374, filed November 21, 2026 (Entry ID 5708596)
- Respondents' Notice of the Army's Intent to Respond to Immediate Threat Under RCRA's Emergency Exclusion, with Declaration of Col. Aaron C. Teller, No. 26-3374, filed November 21, 2026 (Entry ID 5708596)
- Respondents' Notice of the Army's Intent to Respond to Immediate Threat Under RCRA's Emergency Exclusion, with Declaration of Col. Aaron C. Teller, No. 26-3374, filed November 21, 2026 (Entry ID 5708596)
- Federal respondents' court filing on Army plan (PDF) (hosted copy)
- Added to this timeline
- 2026-11-24 00:35 UTC
- First added
- 2026-11-23 23:22 UTC
- Record
evt-2026-11-21-doj-filing.r1
View correction history (1 earlier version)
Version added 2026-11-23 23:22 UTC
- Headline then
- DOJ filing states Army intent
- Date then
- November 21, 2026
- Description then
- A Justice Department filing said the Army intended to invoke an emergency exclusion and act on November 24. This was a stated intent, not court approval.
- What changed and why
- Adds the archived docket copy (Entry ID 5708596) and the notice's exact wording; the earlier record cited only a third-party copy.
- Updated by
evt-2026-11-21-doj-filing.r1, added 2026-11-24 00:35 UTC- Record
evt-2026-11-21-doj-filing
-
· Court order
Court temporarily pauses EPA permit
The federal appeals court hearing the challenge (the Eighth Circuit) put the EPA emergency permit on a temporary court hold while it considered the request for an emergency stay.
A temporary court hold (an “administrative stay”) is not a decision on the underlying legal challenge. The order is dated November 19; the court's later opinion says it was issued November 20, the date used here.
Source: Eighth Circuit administrative stay order, No. 26-3374 (PDF)
Legal details & supporting records
As recorded
In case No. 26-3374 the Eighth Circuit administratively stayed the EPA emergency permit pending a ruling on the emergency motion. An administrative stay temporarily pauses the permit while the court considers the motion. It is not a decision on the merits. Date: The order is dated November 19, 2026 on its face; the court's November 23 opinion (p. 3) says the court issued it on November 20, 2026. This Timeline places it on November 20, following the later opinion.
Sources
- Eighth Circuit administrative stay order, No. 26-3374 (PDF)
- Opinion (per curiam), Iowa Environmental Council v. EPA, No. 26-3374, filed November 23, 2026 (Entry ID 5708974) (date per opinion)
- Added to this timeline
- 2026-11-24 00:43 UTC
- First added
- 2026-11-23 23:22 UTC
- Record
evt-2026-11-19-eighth-circuit-admin-stay.r2
View correction history (2 earlier versions)
Version added 2026-11-24 00:39 UTC
- Headline then
- Eighth Circuit enters administrative stay
- Date then
- November 20, 2026
- Description then
- In case No. 26-3374 the Eighth Circuit administratively stayed the EPA emergency permit pending a ruling on the emergency motion. An administrative stay temporarily pauses the permit while the court considers the motion. It is not a decision on the merits.
- What changed and why
- Shows both dates (order dated November 19 on its face; opinion says issued November 20) and cites both court documents. Drops the reliance on the hosted file name, which is not independent evidence of the order date (reviewer, 2026-11-24).
- Updated by
evt-2026-11-19-eighth-circuit-admin-stay.r2, added 2026-11-24 00:43 UTC- Record
evt-2026-11-19-eighth-circuit-admin-stay.r1
- Eighth Circuit administrative stay order, No. 26-3374 (PDF)
- Opinion (per curiam), Iowa Environmental Council v. EPA, No. 26-3374, filed November 23, 2026 (Entry ID 5708974) (supporting source)
Version added 2026-11-23 23:22 UTC
- Headline then
- Eighth Circuit enters administrative stay
- Date then
- November 19, 2026
- Description then
- In case No. 26-3374 the Eighth Circuit administratively stayed the EPA emergency permit pending a ruling on the emergency motion. An administrative stay temporarily pauses the permit while the court considers the motion. It is not a decision on the merits.
- What changed and why
- Redated from November 19 to November 20, 2026: the Eighth Circuit's opinion states "On November 20, 2026, this Court issued an administrative stay"; confirmed by the project owner on 2026-11-24. The record ID keeps its original date so earlier links still resolve.
- Updated by
evt-2026-11-19-eighth-circuit-admin-stay.r1, added 2026-11-24 00:39 UTC- Record
evt-2026-11-19-eighth-circuit-admin-stay
-
· Government action
Iowa activates emergency operations center
The Governor of Iowa activated the State Emergency Operations Center ahead of the planned detonation.
Source: Gov. Reynolds activates State Emergency Operations Center ahead of planned detonation
Additional sources & record details
As recorded
The Governor of Iowa activated the State Emergency Operations Center ahead of the planned detonation.
Sources
- Added to this timeline
- 2026-11-23 23:22 UTC
- Record
evt-2026-11-20-iowa-eoc
-
· Announcement
Army, HHS and EPA issue joint statement
The Department of the Army, the Department of Health and Human Services and EPA issued a joint statement on the controlled detonation.
Source: Update: Iowa Army Ammunition Plant, Middletown, Iowa · archived copy
Additional sources & record details
As recorded
The Department of the Army, the Department of Health and Human Services and EPA issued a joint statement on the controlled detonation.
Sources
- Added to this timeline
- 2026-11-23 23:22 UTC
- Record
evt-2026-11-20-joint-statement
-
· Court filing
Legal challenge seeks temporary hold on EPA permit
Those challenging the EPA emergency permit in the Eighth Circuit (the “petitioners”) asked the court for an emergency stay, which would put the permit on hold.
Source: Petitioners' emergency motion for stay (PDF)
Legal details & supporting records
As recorded
Petitioners asked the Eighth Circuit for an emergency stay of the EPA emergency permit.
Sources
- Added to this timeline
- 2026-11-23 23:22 UTC
- Record
evt-2026-11-19-petitioners-motion
-
· Schedule change
Army reschedules detonation for November 23
The Army announced that the detonation was postponed to November 23.
Date replaced by a later announcement: Army reschedules detonation for November 25
Source: Postponed lead azide detonation
Additional sources & record details
As recorded
The Army announced the detonation was postponed to November 23, 2026.
- Event status at the time
- Not yet happened · announced date November 23, 2026
Sources
- Postponed lead azide detonation
- With Little Time Before Lead Azide Detonation, Iowa Scientists and Residents Assemble Monitoring Plans (supporting source)
- Court further delays lead azide detonation at Middletown plant (supporting source)
- Added to this timeline
- 2026-11-23 23:22 UTC
- Record
evt-2026-11-19-army-postponement
-
· Document release
Army lists environmental assessment and related findings
The Army listed its environmental assessment of the detonation and a companion finding it calls a “mitigated finding”. This timeline does not summarize their contents.
Source: Environmental Assessment for the lead azide detonation (PDF)
Additional sources & record details
As recorded
The Army listed its Environmental Assessment and the companion mitigated finding. Contents are not restated here.
Sources
- Added to this timeline
- 2026-11-23 23:22 UTC
- Record
evt-2026-11-18-army-ea
-
· Army advisory
Army publishes plume projection maps
An Army advisory included computer-generated maps estimating where lead could travel through the air and settle on the ground, made for the November 20 plan.
The maps are weather-dependent predictions, not measurements. They are not reproduced on this site.
Date replaced by a later announcement: Army reschedules detonation for November 23
Source: Army public advisory with modeled projections, November 18 (PDF)
Additional sources & record details
As recorded
Army advisory with modeled, weather-dependent projections for the November 20 plan. Projections are predictions, not measurements, and are not reproduced here. See the Army index for current notifications.
- Event status at the time
- Not yet happened · announced date November 20, 2026
Sources
- Army public advisory with modeled projections, November 18 (PDF)
- Army Sustainment Command: Iowa Army Ammunition Plant updates index
Army public advisory with air and surface projection maps (November 18, 2026)
Modeled, weather-dependent projections (computer estimates) for the superseded November 20 plan. They do not represent measured lead or a current forecast. Iowa HHS reports that the Army previously released two environmental projection maps.
- Published
- November 18, 2026 by U.S. Army
- Made for
- November 20, 2026 plan (superseded)
- Status
- Replaced: the plan it was made for was superseded
- Map coverage
- Document only (images in a PDF); not drawn on the map
- Verification
- Original document not archived here
- Record
prj-army-2026-11-18-advisory-maps· added to this timeline 2026-11-23 23:22 UTC
- Added to this timeline
- 2026-11-23 23:22 UTC
- Record
evt-2026-11-18-army-projection-advisory
-
· Army advisory
Army announces November 20 detonation plan
An Army advisory announced two controlled detonations for November 20 at about noon, and asked residents of the Middletown City Park neighborhood to leave from 8 a.m. to 2 p.m.
Date replaced by a later announcement: Army reschedules detonation for November 23
Source: IAAAP public advisory (November 15, 2026)
Additional sources & record details
As recorded
An Army public advisory announced two controlled detonations for November 20, 2026, at approximately noon, with residents of the Middletown City Park neighborhood asked to vacate from 8 a.m. to 2 p.m.
- Event status at the time
- Not yet happened · announced date November 20, 2026 (Advisory states approximately noon local time.)
Sources
- Added to this timeline
- 2026-11-23 23:22 UTC
- Record
evt-2026-11-15-army-advisory
-
· Permit
EPA emergency permit for storage and detonation takes effect
EPA's regional office issued an emergency permit for storing the lead azide at the plant and destroying it by detonating it in place. The permit runs from November 13, 2026 through February 11, 2027.
Source: Iowa Army Ammunition Plant, Middletown, Iowa · archived copy
Legal details & supporting records
As recorded
EPA Region 7 issued an emergency permit covering storage and treatment of lead azide by in-place detonation at the plant, effective November 13, 2026 through February 11, 2027.
- Effective
- November 13, 2026, 00:00 Central
- Published
- EPA notice published November 16, 2026
Sources
- Iowa Army Ammunition Plant, Middletown, Iowa
- EPA emergency permit for treatment and storage (redacted PDF)
- Added to this timeline
- 2026-11-23 23:22 UTC
- Record
evt-2026-11-13-epa-emergency-permit
October 2026
-
· Public meeting
Army holds a public open house
The Army held a public open house about the planned lead azide detonation at the plant.
Source: Iowa Army Ammunition Plant public open house recap
Additional sources & record details
As recorded
The Army held a public open house about the planned lead azide detonation at the Iowa Army Ammunition Plant.
- Published
- Army recap published October 28, 2026
Sources
- Added to this timeline
- 2026-11-23 23:22 UTC
- Record
evt-2026-10-15-army-open-house
September 2026
-
· Permit
EPA storage-only permit takes effect
EPA's regional office issued an emergency permit covering storage only, effective September 29. EPA describes it as the third emergency permit for storage at the plant.
Source: EPA Region 7: storage-only emergency permit page · archived copy
Legal details & supporting records
As recorded
EPA Region 7 issued an earlier emergency permit covering storage only, effective September 29, 2026. EPA describes it as the third emergency permit for storage at the plant.
- Published
- EPA public notice publish date November 3, 2026
Sources
- Added to this timeline
- 2026-11-23 23:22 UTC
- Record
evt-2026-09-29-epa-storage-permit
July 2026
-
· Announcement
Army announces an extension
The Army published an announcement of an extension.
The material held here does not say what was extended.
Source: Army public announcement (printable), July 10, 2026
Additional sources & record details
As recorded
An Army public announcement dated July 10, 2026 announced an extension.
Sources
- Added to this timeline
- 2026-11-23 23:22 UTC
- Record
evt-2026-07-10-army-extension
How we maintain this timeline
Newest first, dated by the decision, filing or announcement itself. Each entry restates a cited document. Announced dates that were later changed stay listed as superseded.
Each entry is one real-world event. When our record of an event is corrected (for example, a date confirmed from a later court document, or a better source found), the entry shows the latest version with “Record updated” and keeps every earlier version, what changed and why, under “View correction history”. Links to earlier versions still work.
When an announced date is later changed, both announcements stay on the timeline as separate events, and the earlier one says it was replaced by a later announcement. News reports, official announcements, court filings and court decisions are labeled as such.
“Added to this timeline” is when this tracker recorded an entry, which can be later than the event itself. Record identifiers and archive details are in each entry's details. 4 entries have a correction history.
Every source, with its archived copies and fingerprints, is listed in Sources & Methodology.
What monitoring and reporting are required?
The EPA emergency permit outlines environmental monitoring activities and reports the Army is required to complete.
Some information must be made public. Other reports are submitted to the EPA for review.
Read the permit: EPA emergency permit for treatment and storage (redacted PDF) · archived copy
Current status
The latest status record gives a planned date of November 25, 2026, 09:00 Central; the detonation has not been confirmed. 7 of the 9 requirements are timed from the detonation or its completion, so their deadlines cannot be calculated until that time is confirmed. 2 are timed from other steps that have not been verified: the atmospheric modeling report (due within 24 hours of publication of the preliminary, updated and final plume estimates); the laboratory report and proposed remediation plan (due within five days of receiving validated laboratory data from that sampling).
None has verified completion yet. Not having found evidence of completion does not mean a requirement was missed. Latest legal development: Federal appeals court lifts temporary hold on EPA permit.
Before the detonation
-
Preliminary plume projections
A public estimate of where the plume could travel, based on the weather forecast.
- When: No later than five days before the detonation.
- Type: Public release required
- Status not yet confirmed · deadline cannot yet be calculated
The Army's November 15 advisory included two projection maps and the Army issued updated maps on November 18 (as described in the November 23 opinion, p. 3), but this tracker has not verified either as this deliverable.
Permit wording & verification record
- Permit condition
- Emergency Permit Condition IV.G.1.i, p. 10
- Permit wording
No later than five (5) days prior to the treatment activity, the Permittee shall develop and publicly distribute a preliminary plume impact estimate
- Required report or activity
- Preliminary plume impact estimate using forecasted weather conditions 48 hours prior to the treatment activity
- Organization responsible under the permit
- U.S. Department of the Army (Permittee)
- Recipient
- Public
- Timing (as written)
- No later than five (5) days prior to the treatment activity
- Deadline is based on
- the treatment activity (deadline: no later than 5 days before it). Deadline cannot yet be calculated
- Status as recorded
- undetermined as of November 24, 2026. The permit is in effect: the Eighth Circuit lifted its administrative stay on November 23, 2026. No treatment date is confirmed; the respondents' November 21 notice states an intent to act by November 24, which is a stated intent, not a confirmed date. The Army's November 15 advisory included two projection maps and the Army issued updated maps on November 18 (as described in the November 23 opinion, p. 3), but this tracker has not verified either as this deliverable. Status is undetermined until the trigger is verified.
- Evidence of completion
- No supporting record available. Completion not verified.
- Record updated
- Replaces a blanket "not yet due" with an explicit undetermined status: the trigger has not been verified, so the deadline cannot be placed. Status note now matches the timing field (reviewer, 2026-11-24).
- Record
obl-permit-iv-g-1-i.r2(updatesobl-permit-iv-g-1-i.r1)
- EPA emergency permit for treatment and storage (redacted PDF)
- Opinion (per curiam), Iowa Environmental Council v. EPA, No. 26-3374, filed November 23, 2026 (Entry ID 5708974)
-
Updated plume projections
An updated public estimate using the forecast for the detonation day.
- When: No later than 48 hours before the detonation.
- Type: Public release required
- Status not yet confirmed · deadline cannot yet be calculated
The Army's November 15 advisory included two projection maps and the Army issued updated maps on November 18 (as described in the November 23 opinion, p. 3), but this tracker has not verified either as this deliverable.
Permit wording & verification record
- Permit condition
- Emergency Permit Condition IV.G.1.ii.a, p. 10
- Required report or activity
- Updated plume impact estimate using forecasted weather on the treatment date
- Organization responsible under the permit
- U.S. Department of the Army (Permittee)
- Recipient
- Public
- Timing (as written)
- No later than 48 hours prior to the treatment activity
- Deadline is based on
- the treatment activity (deadline: no later than 48 hours before it). Deadline cannot yet be calculated
- Status as recorded
- undetermined as of November 24, 2026. The permit is in effect: the Eighth Circuit lifted its administrative stay on November 23, 2026. No treatment date is confirmed; the respondents' November 21 notice states an intent to act by November 24, which is a stated intent, not a confirmed date. The Army's November 15 advisory included two projection maps and the Army issued updated maps on November 18 (as described in the November 23 opinion, p. 3), but this tracker has not verified either as this deliverable. Status is undetermined until the trigger is verified.
- Evidence of completion
- No supporting record available. Completion not verified.
- Record updated
- Replaces a blanket "not yet due" with an explicit undetermined status: the trigger has not been verified, so the deadline cannot be placed. Status note now matches the timing field (reviewer, 2026-11-24).
- Record
obl-permit-iv-g-1-ii-a.r2(updatesobl-permit-iv-g-1-ii-a.r1)
- EPA emergency permit for treatment and storage (redacted PDF)
- Opinion (per curiam), Iowa Environmental Council v. EPA, No. 26-3374, filed November 23, 2026 (Entry ID 5708974)
Around the time of the detonation
-
Hourly plume projection updates
Public plume estimates updated every hour.
- When: Beginning six hours before the detonation and every hour after that until it is complete.
- Type: Public release required
- Status not yet confirmed · deadline cannot yet be calculated
Permit wording & verification record
- Permit condition
- Emergency Permit Condition IV.G.1.ii.b, p. 10
- Required report or activity
- Hourly updated plume impact estimates
- Organization responsible under the permit
- U.S. Department of the Army (Permittee)
- Recipient
- Public
- Timing (as written)
- Beginning 6 hours before the treatment activity and every hour thereafter until completion
- Deadline is based on
- 6 hours before the treatment activity (hourly updates until completion). Deadline cannot yet be calculated
- Status as recorded
- undetermined as of November 24, 2026. The permit is in effect: the Eighth Circuit lifted its administrative stay on November 23, 2026. No treatment date is confirmed; the respondents' November 21 notice states an intent to act by November 24, which is a stated intent, not a confirmed date. Status is undetermined until the trigger is verified.
- Evidence of completion
- No supporting record available. Completion not verified.
- Record updated
- Replaces a blanket "not yet due" with an explicit undetermined status: the trigger has not been verified, so the deadline cannot be placed. Status note now matches the timing field (reviewer, 2026-11-24).
- Record
obl-permit-iv-g-1-ii-b.r2(updatesobl-permit-iv-g-1-ii-b.r1)
- EPA emergency permit for treatment and storage (redacted PDF)
- Opinion (per curiam), Iowa Environmental Council v. EPA, No. 26-3374, filed November 23, 2026 (Entry ID 5708974)
-
Environmental monitoring
Monitoring for lead moving into soil, surface water, sediment, groundwater or air, as set out in the Army's permit application and sampling plan.
- When: During the detonation, as specified in the referenced application sections.
- Type: Monitoring activity
- Status not yet confirmed · deadline cannot yet be calculated
Permit wording & verification record
- Permit condition
- Emergency Permit Condition IV.Q.1, p. 14
- Required report or activity
- Monitoring of potential migration of releases to soil, surface water, sediment, groundwater and/or air, per Emergency Permit Application Section 6, Section 11 and Appendix 1 (UFP-QAPP)
- Organization responsible under the permit
- U.S. Department of the Army (Permittee)
- Recipient
- Not stated in the permit condition
- Timing (as written)
- During the treatment activity, per the referenced application sections
- Deadline is based on
- the treatment activity (monitoring during and around it). Deadline cannot yet be calculated
- Status as recorded
- undetermined as of November 24, 2026. The permit is in effect: the Eighth Circuit lifted its administrative stay on November 23, 2026. No treatment date is confirmed; the respondents' November 21 notice states an intent to act by November 24, which is a stated intent, not a confirmed date. Status is undetermined until the trigger is verified.
- Evidence of completion
- No supporting record available. Completion not verified.
- Record updated
- Replaces a blanket "not yet due" with an explicit undetermined status: the trigger has not been verified, so the deadline cannot be placed. Status note now matches the timing field (reviewer, 2026-11-24).
- Record
obl-permit-iv-q-1.r2(updatesobl-permit-iv-q-1.r1)
- EPA emergency permit for treatment and storage (redacted PDF)
- Opinion (per curiam), Iowa Environmental Council v. EPA, No. 26-3374, filed November 23, 2026 (Entry ID 5708974)
After the detonation
-
Final plume impact estimate
A public estimate based on the weather recorded at the time of the detonation.
- When: Within six hours of completion.
- Type: Public release required
- Status not yet confirmed · deadline cannot yet be calculated
Permit wording & verification record
- Permit condition
- Emergency Permit Condition IV.G.1.iii, p. 10
- Permit wording
Within 6 hours of completion of the treatment activity, the Permittee shall update and publicly distribute a final plume impact estimate
- Required report or activity
- Final plume impact estimate using weather conditions documented at the time of the treatment activity
- Organization responsible under the permit
- U.S. Department of the Army (Permittee)
- Recipient
- Public
- Timing (as written)
- Within 6 hours of completion of the treatment activity
- Deadline is based on
- completion of the treatment activity (deadline: within 6 hours after). Deadline cannot yet be calculated
- Status as recorded
- undetermined as of November 24, 2026. The permit is in effect: the Eighth Circuit lifted its administrative stay on November 23, 2026. No completed treatment activity is confirmed. Status is undetermined until the trigger is verified.
- Evidence of completion
- No supporting record available. Completion not verified.
- Record updated
- Replaces a blanket "not yet due" with an explicit undetermined status: the trigger has not been verified, so the deadline cannot be placed. Status note now matches the timing field (reviewer, 2026-11-24).
- Record
obl-permit-iv-g-1-iii.r2(updatesobl-permit-iv-g-1-iii.r1)
- EPA emergency permit for treatment and storage (redacted PDF)
- Opinion (per curiam), Iowa Environmental Council v. EPA, No. 26-3374, filed November 23, 2026 (Entry ID 5708974)
-
Soil and surface sampling begins
Soil sampling and wipe sampling of frequently touched surfaces in the area where the final estimate models the most dust-lead settling (see details for the exact area and which properties are included).
- When: Begins within 24 hours of the detonation.
- Type: Monitoring activity
- Status not yet confirmed · deadline cannot yet be calculated
The sampling area also depends on the IV.G.1.iii post-detonation estimate, which has not been verified.
Permit wording & verification record
- Permit condition
- Emergency Permit Condition IV.U.2.ii, p. 16
- Permit wording
within 24 hours of the treatment activity the Permittee shall initiate both soil sampling and wipe sampling of high-touch surfaces at all parks, public facilities, and private properties to which the Permittee has been granted Rights of Entry within the area of modeled dust-lead deposition ≥ 100 µg/ft² of the post-detonation plume impact estimate that is required under Emergency Permit Condition IV.G.1.iii.
- Required report or activity
- Soil sampling and wipe sampling of high-touch surfaces in the modeled ≥ 100 µg/ft² dust-lead deposition area (parks, public facilities, and private properties with Rights of Entry)
- Organization responsible under the permit
- U.S. Department of the Army (Permittee)
- Recipient
- Not applicable (field activity); results feed the submission in IV.U.2.ii
- Timing (as written)
- Begin within 24 hours of the treatment activity
- Deadline is based on
- the treatment activity (deadline: begin within 24 hours after). Deadline cannot yet be calculated
- Status as recorded
- undetermined as of November 24, 2026. The permit is in effect: the Eighth Circuit lifted its administrative stay on November 23, 2026. No treatment activity is confirmed. The sampling area also depends on the IV.G.1.iii post-detonation estimate, which has not been verified. Status is undetermined until the trigger is verified.
- Evidence of completion
- No supporting record available. Completion not verified.
- Record updated
- Replaces a blanket "not yet due" with an explicit undetermined status: the trigger has not been verified, so the deadline cannot be placed. Status note now matches the timing field (reviewer, 2026-11-24).
- Record
obl-permit-iv-u-2-ii-sampling.r1(updatesobl-permit-iv-u-2-ii-sampling)
- EPA emergency permit for treatment and storage (redacted PDF)
- Opinion (per curiam), Iowa Environmental Council v. EPA, No. 26-3374, filed November 23, 2026 (Entry ID 5708974) (supporting source)
-
Final impact area report
A report on where the plume traveled and settled, using data collected during the detonation.
- When: Within 30 days of completion.
- Type: EPA submission
- Status not yet confirmed · deadline cannot yet be calculated
Permit wording & verification record
- Permit condition
- Emergency Permit Condition IV.Q.2, p. 14
- Permit wording
Within thirty (30) days of completion of the treatment activity, the Permittee shall submit the Final Impact Area Report for the atmospheric dispersion and ground deposition plume to the EPA for review.
- Required report or activity
- Final Impact Area Report summarizing atmospheric dispersion and ground deposition plume modeling and mapping of lead release, using real-time data collected at the time of the treatment activity
- Organization responsible under the permit
- U.S. Department of the Army (Permittee)
- Recipient
- U.S. EPA (for review)
- Timing (as written)
- Within thirty (30) days of completion of the treatment activity
- Deadline is based on
- completion of the treatment activity (deadline: within 30 days after). Deadline cannot yet be calculated
- Status as recorded
- undetermined as of November 24, 2026. The permit is in effect: the Eighth Circuit lifted its administrative stay on November 23, 2026. No completed treatment activity is confirmed. A submission to EPA is not a public release. Status is undetermined until the trigger is verified.
- Evidence of completion
- No supporting record available. Completion not verified.
- Record updated
- Replaces a blanket "not yet due" with an explicit undetermined status: the trigger has not been verified, so the deadline cannot be placed. Status note now matches the timing field (reviewer, 2026-11-24).
- Record
obl-permit-iv-q-2.r2(updatesobl-permit-iv-q-2.r1)
- EPA emergency permit for treatment and storage (redacted PDF)
- Opinion (per curiam), Iowa Environmental Council v. EPA, No. 26-3374, filed November 23, 2026 (Entry ID 5708974)
Other reporting requirements
-
Atmospheric modeling report
A report documenting the settings used for the plume modeling and the maps it produced.
- When: Within 24 hours of publication of the preliminary, updated and final plume estimates.
- Type: EPA submission
- Status not yet confirmed · deadline cannot yet be calculated
Publication of those estimates has not been verified. The Army's November 15 advisory included two projection maps and the Army issued updated maps on November 18 (as described in the November 23 opinion, p. 3), but this tracker has not verified either as this deliverable.
Permit wording & verification record
- Permit condition
- Emergency Permit Condition IV.G.3, p. 11
- Required report or activity
- Atmospheric dispersion modeling report documenting the parameters used and the imagery generated
- Organization responsible under the permit
- U.S. Department of the Army (Permittee)
- Recipient
- U.S. EPA (review and approval)
- Timing (as written)
- Within 24 hours of publication of the plume impact estimates required by IV.G.1.i, IV.G.1.ii.a and IV.G.1.iii
- Deadline is based on
- publication of the plume impact estimates required by IV.G.1.i, IV.G.1.ii.a and IV.G.1.iii (deadline: within 24 hours after). Deadline cannot yet be calculated
- Status as recorded
- undetermined as of November 24, 2026. The permit is in effect: the Eighth Circuit lifted its administrative stay on November 23, 2026. Publication of those estimates has not been verified. The Army's November 15 advisory included two projection maps and the Army issued updated maps on November 18 (as described in the November 23 opinion, p. 3), but this tracker has not verified either as this deliverable. A submission to EPA is not a public release. Status is undetermined until the trigger is verified.
- Evidence of completion
- No supporting record available. Completion not verified.
- Record updated
- Replaces a blanket "not yet due" with an explicit undetermined status: the trigger has not been verified, so the deadline cannot be placed. Status note now matches the timing field (reviewer, 2026-11-24).
- Record
obl-permit-iv-g-3.r2(updatesobl-permit-iv-g-3.r1)
- EPA emergency permit for treatment and storage (redacted PDF)
- Opinion (per curiam), Iowa Environmental Council v. EPA, No. 26-3374, filed November 23, 2026 (Entry ID 5708974)
-
Laboratory report and proposed remediation plan
The laboratory report from the soil and surface sampling, and a proposed first-phase cleanup plan with a schedule.
- When: Within five days of receiving validated laboratory data from that sampling.
- Type: Recipient not specified in this permit condition
- Status not yet confirmed · deadline cannot yet be calculated
Neither the sampling nor receipt of validated data is confirmed. The condition names no recipient and requires no public release.
Permit wording & verification record
- Permit condition
- Emergency Permit Condition IV.U.2.ii, p. 16
- Permit wording
Within five (5) days of receipt of the validated analytical data resulting from such sampling, the Permittee shall submit the laboratory report and a proposed Closure Plan Phase 1 Remediation Work Plan (including implementation schedule) based on the analytical data.
- Required report or activity
- Laboratory report of the IV.U.2.ii sampling and a proposed Closure Plan Phase 1 Remediation Work Plan, including an implementation schedule
- Organization responsible under the permit
- U.S. Department of the Army (Permittee)
- Recipient
- Not named in this condition
- Timing (as written)
- Within 5 days of receipt of the validated analytical data from the IV.U.2.ii sampling
- Deadline is based on
- receipt of validated analytical data from the IV.U.2.ii sampling (deadline: within 5 days after). Deadline cannot yet be calculated
- Status as recorded
- undetermined as of November 24, 2026. The permit is in effect: the Eighth Circuit lifted its administrative stay on November 23, 2026. Neither the sampling nor receipt of validated data is confirmed. The condition names no recipient and requires no public release. Status is undetermined until the trigger is verified.
- Evidence of completion
- No supporting record available. Completion not verified.
- Record updated
- Replaces a blanket "not yet due" with an explicit undetermined status: the trigger has not been verified, so the deadline cannot be placed. Status note now matches the timing field (reviewer, 2026-11-24).
- Record
obl-permit-iv-u-2-ii-work-plan.r1(updatesobl-permit-iv-u-2-ii-work-plan)
- EPA emergency permit for treatment and storage (redacted PDF)
- Opinion (per curiam), Iowa Environmental Council v. EPA, No. 26-3374, filed November 23, 2026 (Entry ID 5708974) (supporting source)
Full permit requirements & verification records
Status note shared by every record: The permit is in effect: the Eighth Circuit lifted its administrative stay on November 23, 2026. Status is undetermined until the trigger is verified.
| Condition | Required report or activity | Organization responsible under the permit | Recipient | Type | Timing | Status | Evidence of completion | Source |
|---|---|---|---|---|---|---|---|---|
| Emergency Permit Condition IV.G.1.i | Preliminary plume impact estimate using forecasted weather conditions 48 hours prior to the treatment activityNo later than five (5) days prior to the treatment activity, the Permittee shall develop and publicly distribute a preliminary plume impact estimate | U.S. Department of the Army (Permittee) | Public | Public release required | No later than five (5) days prior to the treatment activity | Status not yet confirmed as of November 24, 2026 | No supporting record available |
|
| Emergency Permit Condition IV.G.1.ii.a | Updated plume impact estimate using forecasted weather on the treatment date | U.S. Department of the Army (Permittee) | Public | Public release required | No later than 48 hours prior to the treatment activity | Status not yet confirmed as of November 24, 2026 | No supporting record available |
|
| Emergency Permit Condition IV.G.1.ii.b | Hourly updated plume impact estimates | U.S. Department of the Army (Permittee) | Public | Public release required | Beginning 6 hours before the treatment activity and every hour thereafter until completion | Status not yet confirmed as of November 24, 2026 | No supporting record available |
|
| Emergency Permit Condition IV.Q.1 | Monitoring of potential migration of releases to soil, surface water, sediment, groundwater and/or air, per Emergency Permit Application Section 6, Section 11 and Appendix 1 (UFP-QAPP) | U.S. Department of the Army (Permittee) | Not stated in the permit condition | Monitoring activity | During the treatment activity, per the referenced application sections | Status not yet confirmed as of November 24, 2026 | No supporting record available |
|
| Emergency Permit Condition IV.G.1.iii | Final plume impact estimate using weather conditions documented at the time of the treatment activityWithin 6 hours of completion of the treatment activity, the Permittee shall update and publicly distribute a final plume impact estimate | U.S. Department of the Army (Permittee) | Public | Public release required | Within 6 hours of completion of the treatment activity | Status not yet confirmed as of November 24, 2026 | No supporting record available |
|
| Emergency Permit Condition IV.U.2.ii | Soil sampling and wipe sampling of high-touch surfaces in the modeled ≥ 100 µg/ft² dust-lead deposition area (parks, public facilities, and private properties with Rights of Entry)within 24 hours of the treatment activity the Permittee shall initiate both soil sampling and wipe sampling of high-touch surfaces at all parks, public facilities, and private properties to which the Permittee has been granted Rights of Entry within the area of modeled dust-lead deposition ≥ 100 µg/ft² of the post-detonation plume impact estimate that is required under Emergency Permit Condition IV.G.1.iii. | U.S. Department of the Army (Permittee) | Not applicable (field activity); results feed the submission in IV.U.2.ii | Monitoring activity | Begin within 24 hours of the treatment activity | Status not yet confirmed as of November 24, 2026 | No supporting record available |
|
| Emergency Permit Condition IV.Q.2 | Final Impact Area Report summarizing atmospheric dispersion and ground deposition plume modeling and mapping of lead release, using real-time data collected at the time of the treatment activityWithin thirty (30) days of completion of the treatment activity, the Permittee shall submit the Final Impact Area Report for the atmospheric dispersion and ground deposition plume to the EPA for review. | U.S. Department of the Army (Permittee) | U.S. EPA (for review) | EPA submission | Within thirty (30) days of completion of the treatment activity | Status not yet confirmed as of November 24, 2026 | No supporting record available |
|
| Emergency Permit Condition IV.G.3 | Atmospheric dispersion modeling report documenting the parameters used and the imagery generated | U.S. Department of the Army (Permittee) | U.S. EPA (review and approval) | EPA submission | Within 24 hours of publication of the plume impact estimates required by IV.G.1.i, IV.G.1.ii.a and IV.G.1.iii | Status not yet confirmed as of November 24, 2026 | No supporting record available |
|
| Emergency Permit Condition IV.U.2.ii | Laboratory report of the IV.U.2.ii sampling and a proposed Closure Plan Phase 1 Remediation Work Plan, including an implementation scheduleWithin five (5) days of receipt of the validated analytical data resulting from such sampling, the Permittee shall submit the laboratory report and a proposed Closure Plan Phase 1 Remediation Work Plan (including implementation schedule) based on the analytical data. | U.S. Department of the Army (Permittee) | Not named in this condition | Recipient not specified in this permit condition | Within 5 days of receipt of the validated analytical data from the IV.U.2.ii sampling | Status not yet confirmed as of November 24, 2026 | No supporting record available |
|
Earlier versions of each record are in the release data.